Minutes:
In attendance for this item were:
Lucy Hodgson, Cabinet Member with Responsibility (CMR) for Communities
Karen May, CMR for Transformation and Commissioning
Andrew Spice, Strategic Director for Commercial & Change
Michael Hudson, Chief Financial Officer (CFO)
Hannah Needham, Assistant Director for Communities
As part of the Council's development of the 2020/21 budget, the Overview and Scrutiny Panels and the Health Overview and Scrutiny Committee were asked to consider the draft budget proposals within their remit.
Since early 2019, the Panel has received regular budget and performance monitoring information. The latest financial information relating to Period 8 had been included as an appendix to the Budget report. The latest performance information relating to Quarter 2 had been considered by the Panel in December 2019.
The Panel's views would contribute to the Overview and Scrutiny's overall response to the budget which was being discussed by the Overview and Scrutiny Performance Board on 29 January 2020.
The CFO led the Panel through the Budget report highlighting key areas of interest including, the:
The CFO guided the Panel through the summary of efficiencies, reforms and income proposals contained in Appendix 1C of the Cabinet December Budget paper. The Chairman had requested an additional explanatory sheet to help clarify which savings tallied with each budget reference. This was tabled at the meeting. The following main areas were discussed:
CoaCh 4 - Redesign of the provision, collation and use of data across the organisation
The Director highlighted that systems such as Power Bi were currently underused and that with capability being centralised, savings would be gained across the Council if technology was then used to its full capacity. In response to a Members question, the Director advised that this work had an urgent timeframe and would be a top priority for Assistant Director (IT and Digital) when appointed. The Panel was very supportive of this proposal and recognised the significant impact it would have across all areas of the Council.
CoaCh 5 - A review of processes, income generation and structure within HR and OD.
· The Panel was reminded that the Talent Programme had been put on hold this year, but that it would be important going forward to ensure that there was appropriate investment.
· In terms of income generation, the Director commented that there was a number of services which had boosted income generation this year and that more services would be reviewed to ensure maximum effectiveness and efficiency. It was stressed that any services provided outside of the organisation must serve a specific purpose and cover their own costs.
· The CMR (Communities) emphasised the importance of enabling services such as the Archives and Archaeology Service to extend their income generating potential. The Chairman asked to be supplied with details of their recent activity.
· The Assistant Director (Communities) advised that the Archives and Archeology Services had a balanced budget and a small surplus was expected.
· The Archaeology Service was currently going through an accreditation process, which was expected to be completed by early March and the Panel would be advised of the outcome in due course. Further opportunities for income generation would also be explored.
CoaCh 6 - A review of processes, income generation and structure within IT
Identifying efficiency savings in IT would be led by the new Assistant Director (IT and Digital) when appointed. An example of this may involve the Council ceasing to provide a Wi-Fi connection to schools, a service which the Council had historically carried out, but gained no income for.
CoaCh 7 - A review of processes, income generation and structure within Engagement and Communication Services
This was about centralising services and trying to get more for less
CoaCh 9 – Contract Review
The Panel was informed that the contract relating to the provision of support for education services (Babcock) was to be brought back in house and the work would be dovetailed with that of current teams, allowing for some modest savings to be achieved. In response to a question, the CMR (Transformation and Commissioning) confirmed that work was always ongoing to review the suitability of contracts to ensure value for money for Worcestershire residents.
CoaCh 10 – Rationalise property maintenance costs
The Director advised the Panel that the £300k of efficiency savings for 2021/22 were planned to be achieved through rationalising of property maintenance costs. Currently, two staff were based within the Council and the bulk of the Services was delivered through Place Partnership Ltd. Every service would be reviewed when the contract was due for renewal to ensure best value
Corp 1 – Budget Reductions across the Council
The CFO advised that following an analysis of spend, specific contracts had been identified where efficiency savings could be achieved to meet this target.
Corp 2 - Review of Admin Functions
A review of administrative functions across the Council was planned, with the intention to set up a corporate Executive Support function, which would provide an efficient centralised support function.
Corp 3 – Centralising Finance Transactions
The Panel was informed that there were currently over 2,000 staff who could place orders, but that the number of transactions varied considerably. It was anticipated that a proposal to centralise financial transactions would allow for considerable efficiencies to be achieved and a tighter control of spend.
Members raised a number of issues and questions as follows:
The Panel was invited to agree comments which the Chairman would contribute towards the OSPB's response to consultation on the 2020/21 budget on 29 January 2020. After some discussion, a summary of the key points was agreed as follows:
· Scrutiny of the draft budget was complicated by a lack of reference between the notes and the budget appendices. It would be highly beneficial moving forward for areas where savings were projected, reserves were used or where there were areas of significant change, to reference these directly in the budget pages.
· The budget preparation was hindered by the fact that Members’ work had been based on the 20 December Cabinet Budget Report, and some figures had changed in the recently published Budget Report for 30 January Cabinet. Whilst acknowledging that changes were largely due to Directorate restructuring and changes to grants from Central Government, members asked that in future, the reporting be made clearer and easier to understand.
· The Panel felt that in order for the redesign of the provision, collation and use of data across the organisation (CoaCh 4) to be achieved, it was essential that the new Assistant Director for IT and Digital and appropriate Information Technology were in place as a matter of urgency, to enable this and other efficiencies and productivity improvements to be implemented.
· It was clear that the focus on all services being delivered in the most efficient and effective way and best value for Worcestershire residents was being achieved. The Panel fully supported the continuing work to review all contracts to ensure this continued.
· The Panel acknowledged the ongoing performance was meeting expectations and complimented the Officers on the financial performance.
· The Chairman of the Overview and Scrutiny Performance Board expressed concern about the review of processes, income generation and structure within Legal Services (CoaCh 3) and the impact on the Scrutiny function. The Panel noted the Chairman’s comments in respect of importance of resources for the Scrutiny function.
Supporting documents: