Agendas, Meetings and Minutes - Agenda and minutes

Agenda and minutes

Venue: Online only

Contact: Alyson Grice/Alison Spall  Overview and Scrutiny Officers

Media

Items
No. Item

1.

Apologies and Welcome

Minutes:

Apologies were received from Councillors Allah Ditta, Panel Member and Marc Bayliss, Cabinet Member with Responsibility.

2.

Declarations of Interest and of any Party Whip

Minutes:

None.

3.

Developer Funded Highways Infrastructure - Update Report pdf icon PDF 311 KB

Additional documents:

Minutes:

In attendance for this item were:

 

Ian Bamforth, Senior Programme Manager

Adrian Tuck, Section 278 and 38 Development Control Manager

Paul Smith, Assistant Director for Highways and Transport Operations

 

The Panel considered an update report on the Council’s work on developer funded highways infrastructure, in particular the time taken for planning submissions from developers to meet the criteria for approval. A presentation was also given by the Senior Programme Manager.

 

The Programme Manager advised that a review of key areas of the Council’s 278/38 Development Control activity had been started in January 2021. The review was to take account of key issues raised by the Panel as well as issues identified by the Management Team. A working group with developers had now been established and was meeting every 3 months. Areas of discussion, and upon which progress to date had been made, included:

 

·         The review of the streetlighting design process

·         Technical approval process and the 4 submissions escalation process

·         Early planning engagement

·         A protocol for working effectively together.

 

The Panel was informed that the street lighting technical design process had been reviewed and agreed timescales and performance measures put in place. The Programme Manager highlighted that the average duration for completion of the design process had previously been 193 days, but that the review had concluded that 91 days was an achievable target, provided all timescales were met by the Council and the developer. The process was currently being tested and carefully monitored, with monthly performance figures being produced. Where issues did arise, these were being addressed proactively as the trial progressed. It was noted that this model would be used as the basis for the wider technical approval process.

 

In terms of the design technical approval process, the Panel was informed that a thorough review was underway and revised elements were being implemented. Key improvements to the process included offering early review meetings to developers, having more focussed milestones for each section of the process, a joint meeting with the developer if a 3rd submission was required and if the 4th submission stage was reached, instigating the escalation procedure. The latter would ensure that if the process was not progressing at an adequate pace and a 4th submission stage was reached, the matter would be escalated to Senior Managers for them to review with the developer and identify what obstacles were causing the delay.

 

Alongside the above, the Programme Manager explained that there was a review of the schemes register, currently with around 474 schemes active at this point. This review would be completed within the next 6 to 8 weeks, following which the full list would be made available to the Panel to review.

 

The Panel was also informed that a resource plan had been agreed to ensure that the Development Control Team had sufficient capacity to deal with the number of developments involving Section 38/278 activity. Additional contractor  resource had been brought in as well as additional engineer posts being advertised. A joint Officer post was also  ...  view the full minutes text for item 3.

4.

Cyclical Drainage - Update on Online Mapping System for Gullies pdf icon PDF 219 KB

Additional documents:

Minutes:

In attendance for this item were:

 

Elliot Pritchard, Head of Highways Operations

Paul Smith, Assistant Director for Highways and Transport Operations

 

The Panel had requested an update on cyclical drainage in respect of the Council’s online mapping system for gullies. The Chairman advised the Panel that drainage and gully issues resulted in large numbers of public enquiries and that this new system being developed would provide up to date information helping to make the process more efficient for all concerned.

 

The Head of Highways Operations had updated his presentation and he led the meeting through the information contained therein. He provided a recap on the development of the online system which would enable users to access up to date information about gullies and drainage systems across the county. There were several stages to the development process and to date work had focussed on ensuring the accuracy of the source data, developing the mapping functionality, and holding an online mapping trial. The latter had resulted in useful feedback from Members being obtained, which had then been used to further enhance the system.

 

The Panel was informed that work was also ongoing in building a ‘Report-It’ system, aimed at enabling the process of identifying and reporting drainage issues to be simplified and made freely accessible to the public. Other work was focussed on developing links to the Engineers Advisory database so that issues could be identified where there were frequent problems being raised and in cases where an engineering solution might be required.

 

The Head of Highways Operations set out a timetable for next steps which included:

 

·         Week commencing 9 August – a live demonstration of GIS Gully Mapping system to members of the Panel

·         Week commencing 30 August – all County Councillors to be provided with a link and password for the system

·         Mid-September/October – live demonstration of Report-It function to Panel

·         December – Live Report-It function to be made available on website

 

Members welcomed the development of this system and praised the Officers for their work. In response to a question as to whether the new system would have an impact on delivering a better service, the Panel was advised that the system would allow routine queries to reach the relevant Team much more quickly. In the case of non-routine issues, where the gullies required more than emptying, the system would provide accurate information of clusters of defects which needed more detailed investigation. In terms of service levels, the Panel was informed that extra resources had recently been provided allowing for the backlog of works to be looked at and dealt with as effectively as possible. There were currently 4 cleansing vehicles in use for drainage works at this time of year, but this could be increased where necessary whenever there was a significant backlog. 

 

The Chairman thanked the Head of Highways Operations and his colleagues for all their work in developing this system, which he felt would be a huge improvement.

5.

Performance and 2020/21 Year-End Budget Monitoring pdf icon PDF 231 KB

Additional documents:

Minutes:

In attendance for this item were:

 

Paul Smith, Assistant Director for Highways and Transport Operations

Rachel Hill, Assistant Director Economy, Major Projects, and Waste

Steph Simcox, Deputy Chief Finance Officer (Service Finance)

Dave Corbett, Management Information Analyst

 

Performance Monitoring – Quarter 4 (January to March 2021)

 

The Panel was presented with a dashboard of performance information relating to indicators from the Directorate level scorecard, the Corporate scorecard and other management information relating to this Panel’s remit for Quarter 4.

 

A range of queries were raised by Members, as set out below:

 

·         Latest figures on Waste – in response to a query about the date of the latest figures, Officers explained that there was always a lag in getting information through, due to the timing of their production with them being linked to a national system. The figures were expected to be available in the Autumn and published in January.

·         Waste Collection – A member commented favourably on the trend of reducing waste from going to landfill and asked how this trend would continue going forward. The Assistant Director advised that as much as possible would continue to be recycled or categorised so that it was treated differently which meant that overtime there would continue to be further reductions in waste being sent to landfill.

·         Ash from Energy to Waste plant – It was confirmed that a lot of the ash and residue from the plant could be recycled. The Cabinet Member advised that much of it went to Hill and Moor where it was processed into 3 different aggregates. A classification was currently awaited from Environment Agency which could lead to a significant increase in recycling.

·         Food wastage – The Assistant Director advised that there was currently consultation taking place nationally on this issue. The County Council as disposal authority and the District Councils as collection authorities were all involved. The outcome of the consultation would be known at the end of the year.

·         Congestion and speeding – A Member queried why the data didn’t currently cover these issues or the impact of them on quality of life. The Chairman advised that these issues hadn’t traditionally been looked at by the Panel, but it was suggested they could be considered for the Work Programme.

·         Potholes – A Member highlighted that the percentage of potholes fixed on time always showed 100%. He queried whether this suggested the timescales were currently too long? He also asked what category of potholes were included in this data? The Assistant Director advised that that there were 4 timescales (1 hour, 24 hour, 7 days, 28 days) for completion of work depending on the severity of the pothole. The Panel was informed that the timescale of 1 hour was to ensure the situation was made safe and that the actual repair might take longer. The Chairman asked that the data to back up the figures be reported to the Panel in more detail. It was also requested that data on a wider range of potholes be  ...  view the full minutes text for item 5.

6.

Work Programme 2021/22 pdf icon PDF 134 KB

Additional documents:

Minutes:

Members were invited to consider the Panel’s current work programme and put forward any amendments, prior to the Overview and Scrutiny Performance Board’s (OSPB) review of the overall scrutiny work programme on 21 July.

 

Developer-funded Highways Infrastructure and Section 278 Technical approval Scrutiny Task Group

 

The Chairman highlighted that in January 2021 the OSPB had approved a Scrutiny proposal for Developer-funded Highways Infrastructure and Section 278 Technical approval, which would be added to the work programme as a legacy for post-election Scrutiny. With the Panel now having received an update report on this issue earlier in the meeting, the Chairman proposed that the OSPB should now be asked to allocate resources for this Task Group so that it could be commenced in October 2021. He felt the delaying of the start date until October was appropriate to allow time for the Officers to progress the outstanding issues. An update report would be sought for the first meeting of the Task Group. The Panel agreed with this course of action which would be recommended to OSPB for approval.

 

Panel’s Work Programme

 

A wide-ranging discussion took place about potential items for inclusion in the Panel’s work programme. The ideas were consolidated into 4 key new areas for the work programme which are shown below and would be submitted to the OSPB on 21 July and on to Council in September:

 

·         How Worcestershire County Council is helping the economy grow

·         Road safety and reduction of speeding by use of built highways infrastructure

·         Congestion – what actions are being taken to reduce the problem

·         Pothole repairs innovation – new ways of repairing

 

The Panel’s potential role and involvement in connection with the renewal of the contract for the Energy to Waste Plant at Hartlebury was raised. The Cabinet Member advised that there would be a clear route for Members’ questions to be submitted in advance of the renewal date.